Unit Name/Code ISY2004 Information Systems Project Management
Assessment Type Report
Assessment Number Four
Assessment Name Project Plan Part 2
Unit Learning
Outcomes Assessed 1, 2, 3 and 5
Due Date and Time Week 12, Friday, 12/06/20 5:00pm
Weighting 35%
Assessment
Description
This part follows on from the previous Time Inc. Assignment 1 Case Study. Now that the project sponsor has approved your Initial Project Plan (delivered in Assessment 1) and associated documents, you may proceed to the planning phase of the project by providing a formal project report for the project sponsor based on the following project planning documents. You may make any appropriate assumptions needed to enable the successful completion of the project. Again, make these assumptions explicit in your report. Use screen shots from your MS Project file. It is a mandatory requirement that you use MS Project. It should be available in the lab. Here are the required sections:
1. Gantt chart
2. Network Diagram (Critical path diagram)
3. Identify at least six milestones for this project using SMART criteria.
4. Resources table
5. Project budget, as calculated by MS Project
6. RACI Table
7. Identify 5 potential risks for this project and write the risk register for all of them. Ensure one of your risks is a positive risk.
8. Construct the Probability/ Impact Matrix for those 5 potential risks.
Referencing and Plagiarism
It is essential to use IN TEXT referencing. If you are using the exact words from a reference then you must use quotation marks.
You can use Chicago Style referencing with numbers, with a listing at the end of the essay. Microsoft Word has an EndNote plugin that makes this style very easy and clear to follow. http://www.chicagomanualofstyle.org/tools_citationguide.html
Alternatively, you can use the more traditional Harvard style, which is more verbose.
http://www.citethisforme.com/harvard-referencing.
Remember that this is a Turnitin assignment and plagiarism will be subject to severe penalties. Please refer to the AIH Academic Misconduct Policy: http://www.aih.nsw.edu.au/content/1-home/8-more-info- tabs/3-official-policies/academic-misconduct-policy.pdf
DO NOT COPY AND PASTE FROM THE INTERNET OR COPY OTHER STUDENTS’ WORK!
Detailed Submission Requirements Before submission, you ensure the submitted work satisfies the following requirements:
• The assignment is to be written in a report format. It must have separate sections for each of the EIGHT tasks
• Submit the report as a Word file through the Turnitin assignment submission tool on Moodle.
• Submit the MS Project file in the separate Moodle assignment submission tool. Disregard any error messages about an incorrect file type. I will be able to download anything that you upload!
• Include a cover sheet that has your name, subject, date, report title and WORD COUNT
• The assignment should not exceed 14 pages and 3,500
Words.
Assessment Criteria Fail Competent Good Excellent
(30) 0-12 12-18 18-24 24-30
1. Gantt Chart
2. Network
Diagram
3. SMART
Milestones Superficial Inappropriate choice of exhibits / Too short or exceeded. Good choice of exhibits. Consistent. Concise and relevant. At least 8
milestones and SMART
criteria Well-presented and written. Logical and precise. Well documented Excellent choice of exhibits and presentation.
(20) 0-8 8-12 12-16 16-20
4. Resources
Table Incorrect format and incomplete. Correct format and most resources in the case study. Very good format and all resources included. Excellent
presentation and all details are correct.
(10) 0-4 4-6 7-8 9-10
5. Project
Budget Incomplete and illogical. Reasonable MS Project bottom up budget Well considered bottom up budget Excellent and insightful analysis
(10) 0-4 4-6 7-8 9-10
6. RACI Table Incorrect or incomplete Mostly correct and
complete RACI allocation All RACI elements accurately included and well presented. Excellent and insightful analysis
(30) 0-12 12-18 18-24 24-30
7 and 8. Risk Management
Plan Incomplete and/or incorrect Mostly correct and all elements attempted. Comprehensive and correct risk management plan. Excellent and insightful analysis
TOTAL 100
Scaled to 30 marks